Edgware Road Footbridge

Download PDF

Overview

  • Contract name:
  • Edgware Road Footbridge
  • Client:
  • Transport for London
  • Duration period:
  • 4 Months
  • Form of contract:
  • Design & Build
  • Value:
  • £600,000
  • Type of work:
  • Infrastructure Maintenance
Edgware road Edgware road Edgware road bridgeEdgware footbridge

The project involved the design and build of a new footbridge over the railway tracks linking the 1st floor of Griffiths House to island platform 4. Prior to the installation, the exisiting bridge was demolished and removed during a weekend possession. A 300T crane was used to lift the new bridge into position.